The fish-friendly, 4-metre-diameter Archimedes screw will generate up to 85 kilowatts and a total of 320 megawatt hours in a typical year. Revenue from feed-in tariff and electricity sales will be used to maintain the system, the surplus supporting the fuel-poverty-and-carbon-reducing activities of the non-profit Energy Agency.
Features of the scheme:
❖ A hydro scheme providing 100%
green electricity is in keeping with South Ayrshire Council’s long-term
development plan to regenerate the riverside area in a sustainable way and
contribute towards the Council’s Carbon Management Plan
❖ Local benefits include a
source of carbon-free electricity and funds for local projects by the Energy Agency
❖ The turbine will be a local
attraction on the River Ayr Way, displaying information on renewable energy
generation to passers by
❖ The scheme design, including
new smolt chutes and eel passes, will assist the passage of migratory salmon
and eels and the installation of a fish counter in the existing fish pass will
benefit the management of the River Ayr catchment fishery
❖ The scheme will prevent the
emission of an estimated 147 tonnes of CO2-equivalent greenhouse gas annually
and continue to generate green energy for many decades, just as the watermills
did from the 13th to 20th centuries
Where are we now - 15 February 2022
Work has continued onsite
throughout December, January and into February 2022. The civil construction contract was extended
to 11th February 2022 to allow remaining works to complete following
high water events throughout the autumn and winter months.
The powerhouse and concrete construction along with the turbine are all in place. The site currently has:
Reinforced concrete construction fully complete
·
All grouting and concreting works in and around
the turbine base and by-wash gate complete
·
The Archimedes screw, connected to its gearbox
and generator
·
The bywash gate and its hydraulic ram
·
The sluice gate
·
Some of the eel and lamprey ladders
·
Cabling connection from College building to
powerhouse complete
·
The electronic control equipment installed
·
Fully installed roof including substructure and
sedum roof
·
The security fencing, complete with 1 additional
section to be fitted
·
All final adjustments to the turbine and by-wash
gate by Vandezande engineers – mostly complete
·
Reinstatement of river bank and walkway – mostly
complete
·
Successful withdrawal of all cofferdams
·
All scaffolds removed
·
All powerhouse decking and steps installed
·
Installation of smolt chutes and remaining eel
and lamprey ladders
· Final visit by Vandezande engineers.
·
Extra section of security fence installed.
·
CCTV security system installed on the
powerhouse.
·
The fish counter installation by Fishtek on
behalf of Marine Scotland Science
·
Display boards are being designed/prepared by
Ayrshire College
·
Official opening taking place 28th
February 2022.
This has resulted in the final
installation phases being delayed into the autumn and winter. High levels of rainfall over this time
resulted in river levels rising rapidly affecting the progress of works. It had
been our earlier intention through careful project planning to avoid this
period, but with the delays encountered with steel shortages we inevitably ran
into this difficult weather season.
Ultimately this has resulted in
the civil construction completion date being extended initially to the end of
January then further into mid-February 2022.
The contractors have worked tirelessly
throughout to meet challenging demands and weekly progress meetings have been
held to ensure we remain on-track for our official ‘opening’ at the end of
February and electricity generation by March 2022. The civil contractors, Bailey Construction
Ltd, have been working their way through finishing touches and are progressing
through a comprehensive ‘snag-list’. Their sub-contracted roof specialists
Skygarden installed the sedum roof over two days in late January.
The smolt/eel/lamprey works that
were scheduled for this week have again been delayed until the water levels
recede, likely w/c 14th February.
The Vandezande engineers have
completed most of their commissioning works on the screw and by-wash gate, with
a final visit expected w/c 14th February.
The electrical contractor TLS
Renewable Consulting Ltd and their sub-contractors have completed most of the
installation of the control system. Testing of this began on 3rd
February and is ongoing in readiness for the G99 grid-connection test with SPEN
on 15th February. A short
test allowing water to flow through and turn the turbine for the first time took
place successfully on 7th February.
We remain confident that we will
achieve successful completion well in advance of the final commissioning
deadline of 18th March 2022.
No comments:
Post a Comment